What is the main Well Control reason for measuring the mud weight and viscosity at the pits?

2 / 17

Use the information below to answer the following question:

Mud weight = 10.2 ppg
Well MD = 12 000 ft
Well TVD = 10 000 ft
Formation pressure = 5500 psi
Drill string pressure loss (friction) = 2500 psi
Annular pressure loss (friction) = 500 psi

What is the well condition?

3 / 17

Which of the following is a “physical barrier”?

4 / 17

What would be an indication provided by the Pressure While Drilling (PWD) tool that indicates a kick while drilling?

5 / 17

Considering the drilling practices below, which is the most appropriate when drilling a gas-bearing top-hole formation?

6 / 17

Which of the following indicators may warn of an increase in formation pressure?

7 / 17

What is kick tolerance?

8 / 17

What is a good practice when there is an increase in connection gas?

9 / 17

Use the information below to answer the following question:

Well Depth = 10200 ft TVD / 12200 ft MD
Mud Weight = 10.2 ppg
Bit Size = 8.5 inch
Open hole capacity = 0.0702 bblf/ft
Drill Pipe capacity = 0.01776 bbl/ft
Drill Pipe Metal displacement = 0.0065 bbl/ft
Casing shoe depth = 8000 ft TVD/MD

After drilling from 12200 ft to 12450 ft MD, what should the pit level have decreased?

10 / 17

The well is flowing with pumps off and there is a gain in the pits.but when the pumps are on, the gain stops. What could be happening downhole?

11 / 17

What is called the highest surface pressure if the well is shut-in due to an uncontrolled flow of gas to the surface?

12 / 17

You are drilling ahead with a 12.25″ bit with an average ROP of 125 ft/hr. For the last hour, there has been no change to the pit level. What should be done?

13 / 17

What is the reason for a pit drill?

14 / 17

What will be the effect of expanding gas on the Equivalent Circulating Density (ECD) measurements with Pressure While Drilling (PWD) tools?

15 / 17

Which of the following actions should be taken while drilling throught a transition zone?

16 / 17

While making a connection, extended flowback time is experienced and decision to shut the well in is made.
SIDPP = 170 psi
SICP = 170 psi
What is the procedure to verify if the long flowback time is due to balloning formation or an influx?

17 / 17

You are drilling ahead with a 12.25″ bit with an average ROP of 50 ft/hr. For the last hour, there has been no change to the pit level. What could be happening downhole?